PAC – Construction going well, costs are in good shape, City council told

Updated drawing of performing arts theatre. (Image: City)

Work on the new Kamloops performing arts centre is coming along just fine, and costs are in good shape, City council was told today (Sept. 1. 2026).

Matt Kachel, the City’s infrastructure delivery divisional manager, told council the project’s highest-risk early construction work, including excavation and shoring, are nearing completion.

“The project’s risk register is currently forecasted to be approximately $5 million under budget, reflecting favourable tender results and the successful retirement of several project risks,” he said of the $211 million theatre complex.

Kachel said the focus will soon shift to foundations, with upcoming procurement including structural steel, mass timber, concrete, waterproofing, electrical systems, HVAC, plumbing and wall systems.

Councillors asked several questions about construction details, including one from Coun. Stephen Karpuk, who wondered where dirt from the excavation is going. Kachel replied that it’s being removed to several sites, including City landfills where it’s used for cover.

Kachel said he expected little impact but as construction costs become more certain, the City may adjust annual borrowing requirements, which could help reduce long-term debt-servicing costs.

He said savings could be used to reduce the overall cost. He also unveiled updated artist’s renderings of the building, which vary somewhat from earlier versions but retain the towering glass lobby area.

Mel Rothenburger's avatar
About Mel Rothenburger (12125 Articles)
ArmchairMayor.ca is a forum about Kamloops and the world. It has more than one million views. Mel Rothenburger is the former Editor of The Daily News in Kamloops, B.C. (retiring in 2012), and past mayor of Kamloops (1999-2005). At ArmchairMayor.ca he is the publisher, editor, news editor, city editor, reporter, webmaster, and just about anything else you can think of. He is grateful for the contributions of several local columnists. This blog doesn't require a subscription but gratefully accepts donations to help defray costs.

1 Comment on PAC – Construction going well, costs are in good shape, City council told

  1. Unknown's avatar Bronwen Scott // September 1, 2026 at 9:36 PM // Reply

    Some of this doesn’t make sense to me and reads more like PR hype.

    How can the project be considered $5 million under budget when:

    1. It’s only a hole in the ground at present?
    2. It’s considerably “over budget” already, since the price tag jumped to $211 million from $145 million?

    If the price tag is actually going to be less than $211 million, instead of reducing the loan amount, wouldn’t it be more prudent to:

    1. Leave that money in the contingency fund that’s getting robbed to pay for the price jump, just in case we need the contingency fund for actual emergencies?
    2. Retain the contingency funds to pay wages in the month before property taxes are paid instead of having to borrow money to make ends meet?

    I’m really hoping that some savvy financial minds are elected this fall. Kamloops can’t afford the way city hall has been handling finances this term.